| Project | Capacity | Status |
|---|---|---|
| Flemington Solar Farm Solar |
17.0 MW | Withdrawn / abandoned |
| Mount Olive Solar Farm Solar |
17.0 MW | Withdrawn / abandoned |
| Solar project X1-106, Sussex County Solar |
16.8 MW | Withdrawn / abandoned |
| Wind Onshore wind |
16.1 MW | Withdrawn / abandoned |
| Big Hill Solar Farm Solar |
16.0 MW | Withdrawn / abandoned |
| Solar project Q195, Maricopa County Solar |
16.0 MW | Withdrawn / abandoned |
| Solar project Q194, Yavapai County Solar |
16.0 MW | Withdrawn / abandoned |
| Solar project X3-033, Sussex County Solar |
16.0 MW | Withdrawn / abandoned |
| Volunteer Way Solar Farm Solar |
16.0 MW | Withdrawn / abandoned |
| Solar project Q211, Yuma County Solar |
16.0 MW | Withdrawn / abandoned |
| Onshore wind project 397, Washington County Onshore wind |
16.0 MW | Withdrawn / abandoned |
| Solar project Q186, Yuma County Solar |
16.0 MW | Withdrawn / abandoned |
| High Desert Solar Solar |
16.0 MW | Withdrawn / abandoned |
| Nuclear project X3-044, Dauphin County Nuclear |
15.0 MW | Withdrawn / abandoned |
| Solar project X2-007, Wayne County Solar |
15.0 MW | Withdrawn / abandoned |
| Sierra View Solar III Solar |
15.0 MW | Withdrawn / abandoned |
| Solar project Company 109, Clark County Solar |
15.0 MW | Withdrawn / abandoned |
| Solar project Q191, Pinal County Solar |
15.0 MW | Withdrawn / abandoned |
| Solar project Q185, Cochise County Solar |
15.0 MW | Withdrawn / abandoned |
| Solar project Q210, Yavapai County Solar |
15.0 MW | Withdrawn / abandoned |
| Solar project X1-024, Salem County Solar |
15.0 MW | Withdrawn / abandoned |
| Milton Solar |
14.9 MW | Withdrawn / abandoned |
| Onshore wind project X2-100, Salem County Onshore wind |
14.4 MW | Withdrawn / abandoned |
| Camden 1 Solar |
14.0 MW | Withdrawn / abandoned |
| Ta-East Lancaster Solar |
14.0 MW | Withdrawn / abandoned |
| Barberton Solar Solar |
14.0 MW | Withdrawn / abandoned |
| Solar project X4-030, Sandusky County Solar |
13.8 MW | Withdrawn / abandoned |
| Jacobs Corner Solar Solar |
13.5 MW | Withdrawn / abandoned |
| Wellfield Solar Solar |
13.4 MW | Withdrawn / abandoned |
| Solar project W4-054, Gloucester County Solar |
12.0 MW | Withdrawn / abandoned |
| Warfield I Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project Q206, Yuma County Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project X1-033, Wyandot County Solar |
12.0 MW | Withdrawn / abandoned |
| Pohatcong II Solar Farm Solar |
12.0 MW | Withdrawn / abandoned |
| Gas project W4-051, Philadelphia County Gas |
12.0 MW | Withdrawn / abandoned |
| Re Lincoln Solar |
12.0 MW | Withdrawn / abandoned |
| Quarry Road Solar Farm Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project Q189, Maricopa County Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project X3-074, Kent County Solar |
11.9 MW | Withdrawn / abandoned |
| Wind Onshore wind |
11.9 MW | Withdrawn / abandoned |
| Other project 404, Sanpete County Other |
11.8 MW | Withdrawn / abandoned |
| Solar project X2-002, Somerset County Solar |
11.2 MW | Withdrawn / abandoned |
| Solar project X1-105, Sussex County Solar |
11.2 MW | Withdrawn / abandoned |
| Gas project GEN-2011-033, Caddo Parish County Gas |
10.8 MW | Withdrawn / abandoned |
| Solar project IC-259, Johnson County Solar |
10.6 MW | Withdrawn / abandoned |
| Solar project X3-072, Sussex County Solar |
10.5 MW | Withdrawn / abandoned |
| Solar project W4-092, Monmouth County Solar |
10.0 MW | Withdrawn / abandoned |
| Sparta Solar Farm Solar |
10.0 MW | Withdrawn / abandoned |
| Lopatcong Solar Farm Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project X4-029, Cumberland County Solar |
10.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)187 ยท 30.0 GW
- PJM (Mid-Atlantic, Midwest)289 ยท 22.9 GW
- Southeast (non-ISO utilities)32 ยท 14.0 GW
- West (non-ISO utilities)157 ยท 12.8 GW
- MISO (Midcontinent)51 ยท 10.5 GW
- SPP (Southwest Power Pool)43 ยท 8,099 MW
- ERCOT (Texas)26 ยท 4,638 MW
- ISO-NE (New England)14 ยท 1,774 MW
- NYISO (New York)9 ยท 1,394 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)