United States βΊ Grid βΊ Interconnection queues βΊ Georgia
SOLAR Β· SOUTHEASTSolar project IC-259, Johnson County
Solar project IC-259, Johnson County is a 10.6 MW solar request withdrawn in the Southeast interconnection queue, in Johnson County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2011 (completed)
- Withdrawn / abandonedAug 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-259
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Wrightsville Primary 230 kV Substation
- Location
- Johnson County, Georgia
- Technology
- Solar: 10.6 MW
- Total requested
- 10.6 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 14 October 2011
- Withdrawn
- August 2012
Location
Marker shows the centre of Johnson County; the queue data does not give exact sites.
Other requests in Johnson County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem