Tedder Hill
Tedder Hill is a 7.5 MW onshore wind farm in Yorkshire and the Humber, England, operated by Venitent Energy Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- Yorkshire and the Humber
- England
Key facts
- Installed capacity
- 7.5 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Venitent Energy Services
- Region
- Yorkshire and the Humber
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- HU19 2BY
- Coordinates
- 53.7523, -0.0265
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Tedder Hill compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 7.5 MW station would generate roughly 17 GWh of electricity in a year, similar to the annual use of about 6,330 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in Yorkshire and the Humber All run by Venitent Energy ServicesNearby generating sites
- Roos Wind Farm (GB) Β· 17.1 MW onshore wind farm2.8 km
- Ottringham Β· 6.07 MW solar farm6.6 km
- Out Newton (RO) Β· 9.1 MW onshore wind farm12.4 km
- Westermost Rough Β· 210 MW offshore wind farm13.0 km
- South Humber Bank Power Station Β· 1,365 MW power station16.9 km
- Killingholme Β· 600 MW open-cycle gas power station17.0 km
- Humber Gateway Β· 219 MW offshore wind farm19.1 km
- Killingholme A Power Station Β· 900 MW power station19.4 km
Also operated by Venitent Energy Services
Venitent Energy Services operates 33 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Tedder Hill Wind cluster
- Developer / operator
- Ventient (formerly Infinis)
- Planning authority
- East Riding of Yorkshire
- Planning reference
- 06/03729/STPLF
- Application submitted
- 11 May 2006
- Permission granted
- 28 January 2010
- Construction started
- 30 October 2012
- Began operating
- 30 August 2013
- Capacity in planning record
- 7.5 MW
- Address
- near Roos, East Riding of Yorkshire, Humberside
- REPD reference
- 3749
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.