πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
WIND Β· OPERATIONAL

Out Newton (RO)

Out Newton (RO) is a 9.1 MW onshore wind farm in Yorkshire and the Humber, England, operated by RWE Npower. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Yorkshire and the Humber
  • England
Project stageOperating
  1. PlanningNov 1998 (completed)
  2. ConsentedSep 2000 (completed)
  3. Construction (completed)
  4. OperatingJan 2002 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
9.1 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
RWE Npower
Region
Yorkshire and the Humber
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
HU12 0TG
Coordinates
53.6689, 0.0994

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Out Newton (RO) compares

348th of 488largest wind farms in the UK register
23rd of 31in Yorkshire and the Humber
0.03%of listed UK wind farms capacity
β‰ˆ 21 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 9.1 MW station would generate roughly 21 GWh of electricity in a year, similar to the annual use of about 7,680 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Yorkshire and the Humber All run by RWE Npower

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Out Newton Wind Farm
Developer / operator
Powergen Renewables Developments Ltd
Planning authority
East Riding of Yorkshire
Planning reference
341/10033
Application submitted
4 November 1998
Permission granted
11 September 2000
Began operating
31 January 2002
Capacity in planning record
9 MW
Address
Southfield Farms Hull, Humberside
REPD reference
2659

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.