Mynydd Clogau
Mynydd Clogau is a 14.5 MW onshore wind farm in Wales, operated by Venitent Energy Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- Wales
Key facts
- Installed capacity
- 14.5 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Venitent Energy Services
- Region
- Wales
- Country
- Wales
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SY16 3DQ
- Coordinates
- 52.5784, -3.4285
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Mynydd Clogau compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 14.5 MW station would generate roughly 33 GWh of electricity in a year, similar to the annual use of about 12,190 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in Wales All run by Venitent Energy ServicesNearby generating sites
- P&L Β· 30.6 MW onshore wind farm10.3 km
- Cemmaes Β· 15.3 MW onshore wind farm18.0 km
- Bryn Titli Β· 9.9 MW onshore wind farm25.3 km
- Garreg Llwyd (GB) Β· 30.4 MW onshore wind farm27.8 km
- Cambrian Β· 58.5 MW onshore wind farm29.1 km
- Rheidol Hydro Scheme Gen 5 Β· 0.08 MW small hydro scheme31.7 km
- Rheidol Hydro Scheme Gen 3 Β· 20.5 MW hydroelectric station32.4 km
- Rheidol Hydro Scheme Gen 2 Β· 20.5 MW hydroelectric station32.4 km
Also operated by Venitent Energy Services
Venitent Energy Services operates 33 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Mynydd Clogau Wind Farm
- Developer / operator
- Renewable Energy Systems (RES)
- Planning authority
- Powys
- Planning reference
- 1998/0669
- Application submitted
- 11 September 1998
- Permission granted
- 23 May 2002
- Began operating
- 1 December 2005
- Capacity in planning record
- 14.5 MW
- Address
- Mynydd Clogau, Mynydd Bwrch-y-gors and Mynydd Cerrigllwydion, near Adfa, Newtown, Powys, Powys
- REPD reference
- 4684
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.