St Francis
St Francis is a 4.33 MW solar farm in South East England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 4.33 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- TN33 9BL
- Coordinates
- 50.8749, 0.4534
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How St Francis compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.33 MW station would generate roughly 3.8 GWh of electricity in a year, similar to the annual use of about 1,400 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by Lightsource BPNearby generating sites
- Natewood Β· 8.98 MW solar farm15.4 km
- Horam Β· 8.12 MW solar farm16.4 km
- Horam Solar Park Β· 2.57 MW solar farm16.7 km
- Wilbees Β· 5 MW solar farm18.8 km
- Bentley Estate Β· 4.78 MW solar farm24.9 km
- Bentley Estate 2 Β· 5 MW solar farm25.0 km
- Little Cheyne Court Β· 59.8 MW onshore wind farm27.7 km
- Upper Clayhill Β· 4.75 MW solar farm28.2 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- St Francis Farm
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Rother
- Planning reference
- RR/2014/558/P
- Application submitted
- 28 February 2014
- Permission granted
- 26 August 2014
- Construction started
- 17 November 2014
- Began operating
- 19 March 2015
- Capacity in planning record
- 4 MW
- Address
- St Francis Farm, Potmans Lane, Catsfield/Bexhill, East Sussex
- REPD reference
- 1324
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.