Horam
Horam is a 8.12 MW solar farm in South East England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 8.12 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- TN21 0JB
- Coordinates
- 50.9313, 0.2377
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Horam compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 8.12 MW station would generate roughly 7.1 GWh of electricity in a year, similar to the annual use of about 2,630 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by Lightsource BPNearby generating sites
- Horam Solar Park Β· 2.57 MW solar farm1.5 km
- Bentley Estate 2 Β· 5 MW solar farm8.9 km
- Bentley Estate Β· 4.78 MW solar farm8.9 km
- Natewood Β· 8.98 MW solar farm9.9 km
- Wilbees Β· 5 MW solar farm10.6 km
- Upper Clayhill Β· 4.75 MW solar farm12.8 km
- St Francis Β· 4.33 MW solar farm16.4 km
- Balcombe Β· 4.96 MW solar farm27.0 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- Vogt Solar
- Planning authority
- Wealden
- Planning reference
- WD/2014/1642
- Application submitted
- 7 August 2014
- Permission granted
- 19 September 2014
- Construction started
- 1 January 2015
- Began operating
- 31 March 2015
- Capacity in planning record
- 8.1 MW
- Address
- Land AND WEST OF HORAM MANOR, HORAM, East Sussex, TN21 0YD
- REPD reference
- 2169
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.