SOLAR Β· OPERATIONAL

Puriton

Puriton is a 4.57 MW solar farm in South West England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningFeb 2011 (completed)
  2. ConsentedMay 2011 (completed)
  3. ConstructionAug 2011 (completed)
  4. OperatingOct 2011 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.57 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
TA6 4TG
Coordinates
51.1757, -2.9675

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Puriton compares

490th of 662largest solar farms in the UK register
120th of 192in South West
0.08%of listed UK solar farms capacity
β‰ˆ 4.0 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.57 MW station would generate roughly 4.0 GWh of electricity in a year, similar to the annual use of about 1,480 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Puriton Solar Farm
Developer / operator
BNRG Renewables
Planning authority
Somerset
Planning reference
42/10/00030
Application submitted
23 February 2011
Permission granted
24 May 2011
Construction started
1 August 2011
Began operating
1 October 2011
Capacity in planning record
4.6 MW
Address
Bridgwater, Somerset, Somerset
REPD reference
1047

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.