Otherton
Otherton is a 2.52 MW solar farm in West Midlands England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- West Midlands
- England
Key facts
- Installed capacity
- 2.52 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- West Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- WR6 5LS
- Coordinates
- 52.1861, -2.2876
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Otherton compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 2.52 MW station would generate roughly 2.2 GWh of electricity in a year, similar to the annual use of about 820 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in West Midlands All run by Greencoat CapitalNearby generating sites
- Defford Β· 50 MW solar farm13.9 km
- High Point Β· 3.75 MW solar farm21.8 km
- Salford Lodge Solar Farm Β· 5 MW solar farm24.5 km
- Robert's Wall Β· 2.56 MW solar farm24.5 km
- Mount Farm Β· 23.1 MW solar farm28.0 km
- Rymes Β· 4.99 MW solar farm29.7 km
- Eaton Hill Β· 0.47 MW solar farm30.3 km
- Home Farm Β· 4.99 MW solar farm31.3 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Otherton Farm
- Developer / operator
- Wirisol (Sun & Soil)
- Planning authority
- Malvern Hills
- Planning reference
- 15/00957/FUL
- Application submitted
- 29 July 2015
- Permission granted
- 18 December 2015
- Construction started
- 21 January 2017
- Began operating
- 21 March 2017
- Capacity in planning record
- 4 MW
- Address
- Otherton Farm, Otherton Lane, Cotheridge, Worcester, Hereford and Worcester, WR6 5LS
- REPD reference
- 5538
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026