πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Oakham

Oakham is a 4.64 MW solar farm in South West England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningMay 2015 (completed)
  2. ConsentedOct 2015 (completed)
  3. ConstructionFeb 2016 (completed)
  4. OperatingFeb 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.64 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BS32 4BS
Coordinates
51.5480, -2.5828

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Oakham compares

482nd of 662largest solar farms in the UK register
117th of 192in South West
0.08%of listed UK solar farms capacity
β‰ˆ 4.1 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.64 MW station would generate roughly 4.1 GWh of electricity in a year, similar to the annual use of about 1,510 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Oakham Farm
Developer / operator
Anesco/Parklands Solar
Planning authority
South Gloucestershire
Planning reference
PT15/2164/F
Application submitted
22 May 2015
Permission granted
22 October 2015
Construction started
18 February 2016
Began operating
22 February 2016
Capacity in planning record
8 MW
Address
Oakham Farm Land At Parklands Almondsbury Bristol South Gloucestershire, Avon, BS32 4BS
REPD reference
1269

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.