SOLAR Β· OPERATIONAL

Laurel Hill

Laurel Hill is a 14.2 MW solar farm in Northern Ireland, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • Northern Ireland
Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Key facts

Installed capacity
14.2 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
Northern Ireland
Country
Northern Ireland
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BT25 1JS
Coordinates
54.4025, -6.2622

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Laurel Hill compares

85th of 662largest solar farms in the UK register
4th of 16in Northern Ireland
0.25%of listed UK solar farms capacity
β‰ˆ 12 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 14.2 MW station would generate roughly 12 GWh of electricity in a year, similar to the annual use of about 4,610 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in Northern Ireland All run by Greencoat Capital

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026