Hill Hall Farm
Hill Hall Farm is a 5 MW solar farm in East of England, England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East of England
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- East of England
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- CM7 4SH
- Coordinates
- 51.9642, 0.4097
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Hill Hall Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East of England All run by Lightsource BPNearby generating sites
- The Hydes Β· 10.7 MW solar farm2.2 km
- Thaxted Β· 48 MW solar farm3.1 km
- Tooley Farm Β· 5 MW solar farm8.9 km
- Drapers Farm Β· 6 MW solar farm13.5 km
- Cressing Β· 4.99 MW solar farm19.5 km
- Broxted Β· 31.6 MW solar farm20.0 km
- Melbourn Black Peak Β· 19 MW solar farm27.8 km
- Melbourn Muncey Farm Β· 30.9 MW solar farm29.5 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Land west of Hawkspur Green (Hill Hall Solar)
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Uttlesford
- Planning reference
- UTT/15/0676/FUL
- Application submitted
- 5 March 2015
- Permission granted
- 14 April 2016
- Construction started
- 3 October 2016
- Began operating
- 9 December 2016
- Capacity in planning record
- 4.9 MW
- Address
- Land west of Hill Hall, Hawkspur Green, Little Sampford Road, Little Bardfield, Essex, CM7 4SH
- REPD reference
- 1292
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.