Hadley Farm
Hadley Farm is a 5 MW solar farm in West Midlands England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- West Midlands
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- West Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SY13 3AB
- Coordinates
- 52.9609, -2.7241
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Hadley Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in West Midlands All run by Lightsource BPNearby generating sites
- Bubney Β· 40.4 MW solar farm1.7 km
- Fields Farm (Agden) Β· 5 MW solar farm3.6 km
- Combermere Β· 14 MW solar farm9.4 km
- Trench Farm Β· 5 MW solar farm13.1 km
- Charity Farm - CfD Β· 14.4 MW solar farm16.2 km
- Moor Farm Β· 3.73 MW solar farm20.6 km
- Ebnal Lodge Β· 4.99 MW solar farm20.6 km
- Dairy House Farm Β· 3.37 MW solar farm21.3 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Hadley Solar Farm
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Shropshire
- Planning reference
- 14/02914/FUL
- Application submitted
- 7 July 2014
- Permission granted
- 6 October 2014
- Construction started
- 21 September 2015
- Began operating
- 16 December 2015
- Capacity in planning record
- 6.6 MW
- Address
- Hadley Farm Wrexham Road Whitchurch Shropshire, Shropshire, SY13 3AB
- REPD reference
- 1990
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.