Four Burrows Solar (Kenwyn)

Four Burrows Solar (Kenwyn) is a 7.2 MW solar farm in South West England, operated by RES Group. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningDec 2010 (completed)
  2. ConsentedMar 2011 (completed)
  3. ConstructionJul 2014 (completed)
  4. OperatingJan 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
7.2 MW
Status
Operational
Technology
Solar Β· PV
Operator
RES Group
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
TR4 8JB
Coordinates
50.2899, -5.1408

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Four Burrows Solar (Kenwyn) compares

189th of 662largest solar farms in the UK register
47th of 192in South West
0.13%of listed UK solar farms capacity
β‰ˆ 6.3 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 7.2 MW station would generate roughly 6.3 GWh of electricity in a year, similar to the annual use of about 2,340 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by RES Group

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Four Burrows Solar farm
Developer / operator
TRIG
Planning authority
Cornwall
Planning reference
PA10/07942
Application submitted
2 December 2010
Permission granted
3 March 2011
Construction started
1 July 2014
Began operating
12 January 2015
Capacity in planning record
7.2 MW
Address
Little Lambriggan Penhallow Truro Cornwall, Cornwall, TR4 9NG
REPD reference
1595

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.