Bumpers Farm
Bumpers Farm is a 5 MW solar farm in South East England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- HP27 9RE
- Coordinates
- 51.7465, -0.8962
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Bumpers Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by AnescoNearby generating sites
- Ilmer Β· 5 MW solar farm0.9 km
- Bumpers Farm 2 Β· 12 MW solar farm1.1 km
- Thame Β· 4.79 MW solar farm2.9 km
- Aston Clinton Β· 24.2 MW solar farm12.9 km
- Chalgrove Solar Limited Β· 21.3 MW solar farm14.1 km
- Chalgrove Β· 2.4 MW solar farm16.7 km
- Brook Farm Β· 8.91 MW solar farm18.9 km
- Great Seabrook Β· 4.97 MW solar farm20.6 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Bumpers Farm Phase 1
- Developer / operator
- Solar Planning
- Planning authority
- Buckinghamshire
- Planning reference
- 14/01926/APP
- Application submitted
- 11 July 2014
- Permission granted
- 26 October 2015
- Construction started
- 25 January 2017
- Began operating
- 25 March 2017
- Capacity in planning record
- 5 MW
- Address
- Land North Of Bumpers Farm, Ilmer Lane, Ilmer, Buckinghamshire, Buckinghamshire, HP17 8
- REPD reference
- 2186
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.