SOLAR · ERCOTJuno Solar (Phase II)
Juno Solar (Phase II) is a 147 MW solar request built and operating in the ERCOT interconnection queue, in Borden County, Texas.
Request details
- Queue ID
- 21INR0501
- Grid region
- ERCOT (Texas)
- Location
- Borden County, Texas
- Technology
- Solar: 147 MW
- Total requested
- 147 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 22 March 2020
- Came online
- August 2021
Location
Marker shows the centre of Borden County; the queue data does not give exact sites.
Other requests in Borden County
- Magnet SolarSolar + storage · 503 MW · agreement signed
- Lyra SolarSolar + storage · 500 MW · agreement signed
- Antila SolarSolar · 500 MW · agreement signed
- Lyra StorageSolar + storage · 500 MW · agreement signed
- Juno 3 SolarSolar · 500 MW · agreement signed
- Iron Belt Energy StorageBattery storage · 402 MW · agreement signed
- Uva Creek SolarSolar · 302 MW · agreement signed
- Tumbleweed SolarSolar + storage · 614 MW · in study
- Tumbleweed StorageSolar + storage · 507 MW · in study
- Draco SolarSolar · 500 MW · in study
- Magnet StorageSolar + storage · 427 MW · in study
- Gail Mountain SolarSolar · 244 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem