United States βΊ Grid βΊ Interconnection queues βΊ California
GEOTHERMAL Β· CAISONew Geysers
New Geysers is a 50.0 MW geothermal request withdrawn in the CAISO interconnection queue, in Sonoma County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2007 (completed)
- Withdrawn / abandonedJun 2008 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 187
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Geysers-Fulton 230kV transmission line
- Location
- Sonoma County, California
- Technology
- Geothermal: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 14 March 2007
- Proposed online date
- January 2011
- Withdrawn
- June 2008
Location
Marker shows the centre of Sonoma County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Sonoma County
- Wildhorse Energy CenterBattery storage Β· 122 MW Β· in study
- Mayacamas GeothermalGeothermal Β· 53.0 MW Β· in study
- Borealis Energy StorageBattery storage Β· 314 MW Β· withdrawn
- MyrtleSolar + storage Β· 216 MW Β· withdrawn
- Blitz Energy StorageBattery storage Β· 214 MW Β· withdrawn
- Brix Energy StorageBattery storage Β· 214 MW Β· withdrawn
- North Bay Energy StorageBattery storage Β· 103 MW Β· withdrawn
- North Bay Energy Storage 2Battery storage Β· 102 MW Β· withdrawn
- Pintail Energy StorageBattery storage Β· 100 MW Β· withdrawn
- CPN Wild Horse GeothermalGeothermal Β· 42.0 MW Β· withdrawn
- Kuiper Energy StorageBattery storage Β· 40.5 MW Β· withdrawn
- WGP GeysersGeothermal Β· 35.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem