GAS · PJMEaston Utilities Substation 2
Easton Utilities Substation 2 is a 5.0 MW gas request built and operating in the PJM interconnection queue, in Talbot County, Maryland, connecting to DPL.
Request details
- Queue ID
- K07
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DPL
- Connection point (POI)
- Easton 69kV
- Location
- Talbot County, Maryland
- Technology
- Gas: 5.0 MW
- Total requested
- 5.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 7 May 2003
- Proposed online date
- November 2004
- Came online
- November 2004
Location
Marker shows the centre of Talbot County; the queue data does not give exact sites.
Other requests in Talbot County
- Wye Mills Solar SiteSolar · 10.0 MW · built
- Easton Utilities Substation 2Gas · 5.0 MW · built
- Crockett Solar ProjectSolar · 44.0 MW · withdrawn
- Solar project AA1-143, Talbot CountySolar · 20.0 MW · withdrawn
- Battery storage project AG2-379, Talbot CountyBattery storage · 20.0 MW · withdrawn
- Crockett Solar ProjectSolar · 15.0 MW · withdrawn
- Solar project AA2-150, Talbot CountySolar · 10.0 MW · withdrawn
- Solar project Y1-081, Talbot CountySolar · 3.4 MW · withdrawn
- Battery storage project AC1-224, Talbot CountyBattery storage · 1.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem