Solar + storage project GEN-2022-087, Lamb County

Solar + storage project GEN-2022-087, Lamb County is a 225 MW solar + storage request withdrawn in the SPP interconnection queue, in Lamb County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-087
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Lamb County 230kV Interchange
Location
Lamb County, Texas
Technology
Solar: 225 MW Β· Battery
Total requested
225 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
5 November 2022
Proposed online date
December 2026
Withdrawn
November 2023

Location

Marker shows the centre of Lamb County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Lamb County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem