United States › Grid › Interconnection queues › Maryland
SOLAR · PJMFrosty Valley Energy Center
Frosty Valley Energy Center is a 20.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Anne Arundel County, Maryland, connecting to PPL.
Queue statusConsented
- PlanningQueued Mar 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AF2-434
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Columbia-Geisinger Tap #1 69 kV
- Location
- Anne Arundel County, Maryland
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 31 March 2020
- Proposed online date
- January 2027
Location
Marker shows the centre of Anne Arundel County; the queue data does not give exact sites.
Other requests in Anne Arundel County
- Solar project AG2-617, Anne Arundel CountySolar · 55.0 MW · in study
- Dorchester County Solar 1 ProjectSolar · 20.0 MW · built
- Millersville Landfill & Resource Recovery FacilityGas · 4.0 MW · built
- Fairhaven Battery Energy Storage SystemBattery storage · 2.5 MW · built
- Chapel Energy Storage FacilityBattery storage · 300 MW · withdrawn
- Battery storage project AG2-207, Anne Arundel CountyBattery storage · 275 MW · withdrawn
- Battery storage project AG2-319, Anne Arundel CountyBattery storage · 150 MW · withdrawn
- Battery storage project AG2-225, Anne Arundel CountyBattery storage · 115 MW · withdrawn
- Solar project AF2-435, Anne Arundel CountySolar · 55.0 MW · withdrawn
- Solar project AB2-125, Anne Arundel CountySolar · 3.3 MW · withdrawn
- Battery storage project AB1-041, Anne Arundel CountyBattery storage · 0.0 MW · withdrawn
- Battery storage project AB1-037, Anne Arundel CountyBattery storage · 0.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem