United States › Grid › Interconnection queues › California

SOLAR · CAISO

Wildwood Solar 2

Wildwood Solar 2 is a 15.0 MW solar request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Apr 2012 (completed)
  2. ConsentedSep 2014 (completed)
  3. Construction (completed)
  4. OperatingJan 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
901
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Semitropic-Midway 115 kV line
Location
Kern County, California
Technology
Solar: 15.0 MW
Total requested
15.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
2 April 2012
Agreement signed
25 September 2014
Proposed online date
December 2015
Came online
January 2017

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem