United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

Buffalo Gap 4

Buffalo Gap 4 is a 175 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Nolan County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2017 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0138
Grid region
ERCOT (Texas)
Developer
AES
Connection point (POI)
66216 Bluff Creek 138kV
Location
Nolan County, Texas
Technology
Wind: 175 MW
Total requested
175 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
5 October 2017
Proposed online date
September 2020
Withdrawn
March 2020

Location

Marker shows the centre of Nolan County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Nolan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem