United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTBuffalo Gap 4
Buffalo Gap 4 is a 175 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Nolan County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2017 (completed)
- Withdrawn / abandonedMar 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 19INR0138
- Grid region
- ERCOT (Texas)
- Developer
- AES
- Connection point (POI)
- 66216 Bluff Creek 138kV
- Location
- Nolan County, Texas
- Technology
- Wind: 175 MW
- Total requested
- 175 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 5 October 2017
- Proposed online date
- September 2020
- Withdrawn
- March 2020
Location
Marker shows the centre of Nolan County; the queue data does not give exact sites.
Other requests in Nolan County
- Buffalo Gap 2 Wind RepowerOnshore wind Β· 232 MW Β· agreement signed
- Maryneal WindOnshore wind Β· 182 MW Β· agreement signed
- Buffalo Gap 1 Wind RepowerOnshore wind Β· 120 MW Β· agreement signed
- Sweetwater 2 repowerOnshore wind Β· 7.3 MW Β· agreement signed
- Trent repowerOnshore wind Β· 6.4 MW Β· agreement signed
- Sweetwater 1 repowerOnshore wind Β· 3.0 MW Β· agreement signed
- Champion Wind RepowerOnshore wind Β· 0.3 MW Β· agreement signed
- Harley Hand SolarSolar + storage Β· 506 MW Β· in study
- Harley Hand StorageSolar + storage Β· 503 MW Β· in study
- Themisto SolarSolar Β· 301 MW Β· in study
- Sepanta SolarSolar Β· 217 MW Β· in study
- Sagebrush WindOnshore wind Β· 200 MW Β· in study