United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

North SKY River II Wind

North SKY River II Wind is a 362 MW onshore wind request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2006 (completed)
  2. Withdrawn / abandonedOct 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
149
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
SCE Highwind Sub #2 (proposed) 230 kV
Location
Kern County, California
Technology
Wind: 362 MW
Total requested
362 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
16 November 2006
Proposed online date
December 2010
Withdrawn
October 2008

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem