SOLAR + STORAGE · NYISOELP Granby Solar II
ELP Granby Solar II is a 20.0 MW solar + storage request in interconnection study in the NYISO interconnection queue, in Oswego County, New York, connecting to NM-NG.
Queue statusIn planning
- PlanningQueued Feb 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 1329
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- ELP Granby Solar II LLC
- Connection point (POI)
- Curtis Street - Teall 115 kV
- Location
- Oswego County, New York
- Technology
- Solar: 20.0 MW · Battery
- Total requested
- 20.0 MW
- Study phase
- FES, SIS, FS
- Queue status
- Active
- Entered queue
- 11 February 2022
- Proposed online date
- April 2028
Location
Marker shows the centre of Oswego County; the queue data does not give exact sites.
Other requests in Oswego County
- Oswego Clean EnergySolar · 24.9 MW · in study
- Nine Mile Point UprateNuclear · 168 MW · built
- Nine Mile Point UprateNuclear · 168 MW · built
- Sithe IndependenceGas · 27.0 MW · built
- Sithe IndependenceGas · 27.0 MW · built
- FultonHydro · 1.3 MW · built
- FultonHydro · 1.3 MW · built
- Nine Mile Point Station Unit #3Nuclear · 1,660 MW · withdrawn
- OswegoBattery storage · 1,000 MW · withdrawn
- Sage Creek SolarSolar · 250 MW · withdrawn
- Sage Creek SolarSolar · 250 MW · withdrawn
- Independence BESSBattery storage · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem