🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

GAS · NYISO

Sithe Independence

Sithe Independence is a 27.0 MW gas request built and operating in the NYISO interconnection queue, in Oswego County, New York, connecting to NM-NG.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. ConsentedJan 2023 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
758
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Sithe/Independence Power Partners, LP
Connection point (POI)
Sithe 345kV Substation
Location
Oswego County, New York
Technology
Gas: 27.0 MW
Total requested
27.0 MW
Study phase
SRIS, FS
Queue status
Operational
Entered queue
6 September 2018
Agreement signed
11 January 2023

Location

Marker shows the centre of Oswego County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Oswego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem