BATTERY STORAGE · NYISOIndependence BESS
Independence BESS is a 200 MW battery storage request withdrawn in the NYISO interconnection queue, in Oswego County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1651
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Independence BESS LLC
- Connection point (POI)
- Independence 345kV substation
- Location
- Oswego County, New York
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Queue status
- Withdrawn
- Entered queue
- 14 December 2023
Location
Marker shows the centre of Oswego County; the queue data does not give exact sites.
Other requests in Oswego County
- Oswego Clean EnergySolar · 24.9 MW · in study
- ELP Granby Solar IISolar + storage · 20.0 MW · in study
- Nine Mile Point UprateNuclear · 168 MW · built
- Nine Mile Point UprateNuclear · 168 MW · built
- Sithe IndependenceGas · 27.0 MW · built
- Sithe IndependenceGas · 27.0 MW · built
- FultonHydro · 1.3 MW · built
- FultonHydro · 1.3 MW · built
- Nine Mile Point Station Unit #3Nuclear · 1,660 MW · withdrawn
- OswegoBattery storage · 1,000 MW · withdrawn
- Sage Creek SolarSolar · 250 MW · withdrawn
- Sage Creek SolarSolar · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem