United States βΊ Grid βΊ Interconnection queues βΊ New York
BATTERY STORAGE Β· NYISOOswego
Oswego is a 1,000 MW battery storage request withdrawn in the NYISO interconnection queue, in Oswego County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2008 (completed)
- Withdrawn / abandonedJun 2009 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 314
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Riverbank Power Corporation
- Connection point (POI)
- Oswego complex 345kV
- Location
- Oswego County, New York
- Technology
- Other Storage: 1,000 MW
- Total requested
- 1,000 MW
- Queue status
- Withdrawn
- Entered queue
- 7 October 2008
- Withdrawn
- June 2009
Location
Marker shows the centre of Oswego County; the queue data does not give exact sites.
Other requests in Oswego County
- Oswego Clean EnergySolar Β· 24.9 MW Β· in study
- ELP Granby Solar IISolar + storage Β· 20.0 MW Β· in study
- Nine Mile Point UprateNuclear Β· 168 MW Β· built
- Nine Mile Point UprateNuclear Β· 168 MW Β· built
- Sithe IndependenceGas Β· 27.0 MW Β· built
- Sithe IndependenceGas Β· 27.0 MW Β· built
- FultonHydro Β· 1.3 MW Β· built
- FultonHydro Β· 1.3 MW Β· built
- Nine Mile Point Station Unit #3Nuclear Β· 1,660 MW Β· withdrawn
- Sage Creek SolarSolar Β· 250 MW Β· withdrawn
- Sage Creek SolarSolar Β· 250 MW Β· withdrawn
- Independence BESSBattery storage Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem