United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTAtria Solar MW addition
Atria Solar MW addition is a 61.4 MW solar request withdrawn in the ERCOT interconnection queue, in Liberty County, Texas.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedMar 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 23INR0226
- Grid region
- ERCOT (Texas)
- Developer
- Atria Energy Project, LLC
- Connection point (POI)
- 40770 Hacher 138kV
- Location
- Liberty County, Texas
- Technology
- Solar: 61.4 MW
- Total requested
- 61.4 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Proposed online date
- April 2023
- Withdrawn
- March 2021
Location
Marker shows the centre of Liberty County; the queue data does not give exact sites.
Other requests in Liberty County
- Solar project J1760, Liberty CountySolar Β· 205 MW Β· agreement signed
- Solar project J483, Liberty CountySolar Β· 100 MW Β· agreement signed
- Solar project J3986, Liberty CountySolar Β· 270 MW Β· in study
- Solar project J2075, Liberty CountySolar Β· 200 MW Β· in study
- Solar + storage project J2689, Liberty CountySolar + storage Β· 180 MW Β· in study
- Solar project J2314, Liberty CountySolar Β· 150 MW Β· in study
- Solar project J2165, Liberty CountySolar Β· 145 MW Β· in study
- Gas project J3605, Liberty CountyGas Β· 465 MW Β· withdrawn
- Solar project J2767, Liberty CountySolar Β· 200 MW Β· withdrawn
- Onshore wind project J3972, Liberty CountyOnshore wind Β· 200 MW Β· withdrawn
- Noor SolarSolar Β· 188 MW Β· withdrawn
- Solar project J1277, Liberty CountySolar Β· 130 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem