United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Mustang 2

Mustang 2 is a 153 MW solar request built and operating in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Apr 2014 (completed)
  2. ConsentedAug 2019 (completed)
  3. Construction (completed)
  4. OperatingNov 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1036
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Mustang Switchyard 230 kV
Location
Kings County, California
Technology
Solar: 153 MW
Total requested
153 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
30 April 2014
Agreement signed
26 August 2019
Proposed online date
September 2016
Came online
November 2020

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem