United States › Grid › Interconnection queues › Texas
OTHER · ERCOTLiggett Switch BESS
Liggett Switch BESS is a 9.9 MW other request built and operating in the ERCOT interconnection queue, in Dallas County, Texas.
Request details
- Queue ID
- 24INR0660
- Grid region
- ERCOT (Texas)
- Developer
- ESTX-PLD-ARLINGTON1, LLC
- Connection point (POI)
- Station Name: Liggett Switch (LIGGETT_N8/LIGSW)_x000D_ Load Name or Load Transformer name: LDLXFMR1 _x000D_ Bus #: 1922_x000D_ Voltage: 138 kV
- Location
- Dallas County, Texas
- Technology
- Other: 9.9 MW
- Total requested
- 9.9 MW
- Study phase
- MRD Approved
- Queue status
- Operational
- Entered queue
- 12 March 2024
- Proposed online date
- December 2024
- Came online
- December 2024
Location
Marker shows the centre of Dallas County; the queue data does not give exact sites.
Other requests in Dallas County
- Empire Central BESSBattery storage · 10.0 MW · agreement signed
- Thunder Road Energy StorageBattery storage · 153 MW · in study
- watermelon 6 energy storageBattery storage · 102 MW · in study
- watermelon 2 energy storageBattery storage · 102 MW · in study
- watermelon 1 energy storageBattery storage · 102 MW · in study
- watermelon 3 energy storageBattery storage · 102 MW · in study
- watermelon 4 energy storageBattery storage · 102 MW · in study
- watermelon 5 energy storageBattery storage · 102 MW · in study
- watermelon 8 energy storageBattery storage · 102 MW · in study
- watermelon 7 energy storageBattery storage · 102 MW · in study
- Atlanta TxHSR TPSS DS-1Other · 50.0 MW · in study
- Best Southwest BESSBattery storage · 241 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem