United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Tehachapi Solar

Tehachapi Solar is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2009 (completed)
  2. Withdrawn / abandonedMay 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
522C
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Kern River-Cummings 66kV line
Location
Kern County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
19 August 2009
Proposed online date
December 2013
Withdrawn
May 2012

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem