United States › Grid › Interconnection queues › New York

SOLAR · NYISO

ELP Stillwater Solar

ELP Stillwater Solar is a 20.0 MW solar request built and operating in the NYISO interconnection queue, in Saratoga County, New York, connecting to NM-NG.

Queue statusOperating
  1. PlanningQueued Jun 2018 (completed)
  2. ConsentedMay 2020 (completed)
  3. Construction (completed)
  4. OperatingNov 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
735
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
ELP Stillwater Solar LLC
Connection point (POI)
Luther Forest - Mohican 115kV
Location
Saratoga County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
FES, SIS, FS
Queue status
Operational
Entered queue
12 June 2018
Agreement signed
7 May 2020
Came online
November 2023

Location

Marker shows the centre of Saratoga County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Saratoga County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem