GAS Β· NYISO

Waterford

Waterford is a 530 MW gas request withdrawn in the NYISO interconnection queue, in Saratoga County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2000 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
76
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Calpine Eastern Corporation
Connection point (POI)
NM-NG 230 or 115 kV
Location
Saratoga County, New York
Technology
Gas: 530 MW
Total requested
530 MW
Queue status
Withdrawn
Entered queue
30 October 2000
Withdrawn
March 2019

Location

Marker shows the centre of Saratoga County; the queue data does not give exact sites.