United States βΊ Grid βΊ Interconnection queues βΊ New York
GAS Β· NYISOWaterford
Waterford is a 530 MW gas request withdrawn in the NYISO interconnection queue, in Saratoga County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2000 (completed)
- Withdrawn / abandonedMar 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 76
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Calpine Eastern Corporation
- Connection point (POI)
- NM-NG 230 or 115 kV
- Location
- Saratoga County, New York
- Technology
- Gas: 530 MW
- Total requested
- 530 MW
- Queue status
- Withdrawn
- Entered queue
- 30 October 2000
- Withdrawn
- March 2019
Location
Marker shows the centre of Saratoga County; the queue data does not give exact sites.
Other requests in Saratoga County
- Kce NY 1Battery storage Β· 20.0 MW Β· built
- ELP Stillwater SolarSolar Β· 20.0 MW Β· built
- Kce NY 1Battery storage Β· 20.0 MW Β· built
- ELP Stillwater SolarSolar Β· 20.0 MW Β· built
- Stewarts Bridge HydroHydro Β· 3.0 MW Β· built
- Stewarts Bridge HydroHydro Β· 3.0 MW Β· built
- Mulberry Energy StorageBattery storage Β· 130 MW Β· withdrawn
- Mulberry Energy StorageBattery storage Β· 130 MW Β· withdrawn
- Kce NY 1Other Β· 20.0 MW Β· withdrawn
- West River SolarSolar Β· 20.0 MW Β· withdrawn
- NYSD Energy StorageBattery storage Β· 5.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem