Solar + storage project C2-129, San Juan County

Solar + storage project C2-129, San Juan County is a 57.5 MW solar + storage request withdrawn in the West interconnection queue, in San Juan County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C2-129
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Abajo substation
Location
San Juan County, Utah
Technology
Solar: 57.5 MW Β· Battery
Total requested
57.5 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
13 May 2022
Proposed online date
December 2026

Location

Marker shows the centre of San Juan County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in San Juan County