United States › Grid › Interconnection queues › North Carolina
SOLAR · PJMAulander Earleys Solar
Aulander Earleys Solar is a 80.0 MW solar request withdrawn in the PJM interconnection queue, in Bertie County, North Carolina, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2014 (completed)
- Withdrawn / abandonedMay 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AA1-135
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Earleys-Everetts 230kV
- Location
- Bertie County, North Carolina
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 31 October 2014
- Proposed online date
- November 2019
- Withdrawn
- May 2017
Location
Marker shows the centre of Bertie County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Bertie County
- Sumac SolarSolar · 80.0 MW · agreement signed
- Solar project AG2-382, Bertie CountySolar · 70.0 MW · in study
- Solar project AH1-271, Bertie CountySolar · 40.0 MW · in study
- Kelford Solar ParkSolar · 20.0 MW · built
- Kelford Solar ParkSolar · 3.1 MW · built
- Solar project AD1-132, Bertie CountySolar · 150 MW · withdrawn
- Solar project AG1-312, Bertie CountySolar · 140 MW · withdrawn
- Solar project AG1-437, Bertie CountySolar · 100 MW · withdrawn
- Solar project AC2-063, Bertie CountySolar · 100 MW · withdrawn
- Solar project AG1-438, Bertie CountySolar · 100 MW · withdrawn
- Solar + storage project AE1-026, Bertie CountySolar + storage · 80.0 MW · withdrawn
- Solar + storage project AD2-184, Bertie CountySolar + storage · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem