Ruby Solar Project

Ruby Solar Project is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2009 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
486
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Antelope-Neenach 66kV line
Location
Kern County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
29 June 2009
Proposed online date
November 2013
Withdrawn
July 2012

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.