United States › Grid › Interconnection queues › New Hampshire

OTHER · ISO-NE

Battery Addition

Battery Addition is a 1.5 MW other request withdrawn in the ISO-NE interconnection queue, in Rockingham County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1461
Grid region
ISO-NE (New England)
Connection point (POI)
400 Gosling Road, Portsmouth, New Hampshire. The project will interconnect to the 115kV Bus 1 & 2 at Schiller Substation, directly adjacent to the project’s proposed location on the former coal stor
Location
Rockingham County, New Hampshire
Technology
Oil: 1.5 MW · Battery
Total requested
1.5 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
18 October 2023
Proposed online date
September 2028
Withdrawn
October 2025

Location

Marker shows the centre of Rockingham County; the queue data does not give exact sites.

Power plants in New Hampshire · Transmission lines in New Hampshire

Other requests in Rockingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem