🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Re Mustang

Re Mustang is a 175 MW solar + storage request built and operating in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Jul 2010 (completed)
  2. ConsentedApr 2021 (completed)
  3. Construction (completed)
  4. OperatingOct 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
643W
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Gates-Gregg 230 kV and Gates-McCall 230 kV
Location
Kings County, California
Technology
Solar: 100 MW · Battery: 75.0 MW
Total requested
175 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
31 July 2010
Agreement signed
9 April 2021
Proposed online date
June 2014
Came online
October 2021

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem