ONSHORE WIND · CAISO

Voyager Wind

Voyager Wind is a 220 MW onshore wind request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Mar 2006 (completed)
  2. ConsentedDec 2011 (completed)
  3. Construction (completed)
  4. OperatingApr 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
93
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Windhub Substation 220kV bus
Location
Kern County, California
Technology
Wind: 220 MW
Total requested
220 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
1 March 2006
Agreement signed
22 December 2011
Proposed online date
December 2008
Came online
April 2021

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem