πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

SOLAR Β· PJM

Solar project AA2-168, Prince George's County

Solar project AA2-168, Prince George's County is a 4.0 MW solar request withdrawn in the PJM interconnection queue, in Prince George's County, Maryland, connecting to PEPCO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2015 (completed)
  2. Withdrawn / abandonedAug 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AA2-168
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PEPCO
Connection point (POI)
Prince George's County
Location
Prince George's County, Maryland
Technology
Solar: 4.0 MW
Total requested
4.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 April 2015
Proposed online date
December 2016
Withdrawn
August 2015

Location

Marker shows the centre of Prince George's County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Prince George's County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem