🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

GAS · ISO-NE

UCONN COGEN Facility

UCONN COGEN Facility is a 24.9 MW gas request built and operating in the ISO-NE interconnection queue, in Tolland County, Connecticut.

Queue statusOperating
  1. PlanningQueued Jul 2003 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2005 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
110
Grid region
ISO-NE (New England)
Connection point (POI)
Mansfield 69 kV
Location
Tolland County, Connecticut
Technology
Gas: 24.9 MW
Total requested
24.9 MW
Service type
Other
Study phase
IA Executed
Queue status
Operational
Entered queue
7 July 2003
Proposed online date
October 2005

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Tolland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem