United States › Grid › Interconnection queues › Connecticut
SOLAR · ISO-NECommunity Power Group, 24 Middle Road, Ellington, CT
Community Power Group, 24 Middle Road, Ellington, CT is a 4.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Tolland County, Connecticut.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2021 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1202
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Rockville 14W
- Location
- Tolland County, Connecticut
- Technology
- Solar: 4.0 MW
- Total requested
- 4.0 MW
- Queue status
- Withdrawn
- Entered queue
- 28 December 2021
- Proposed online date
- July 2023
- Withdrawn
- June 2025
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in Tolland County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem