SOLAR · CAISO

Orion Kern County Solar I

Orion Kern County Solar I is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2010 (completed)
  2. Withdrawn / abandonedMar 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
653EC
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Arco Sub 70 kV Bus
Location
Kings County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 September 2010
Proposed online date
July 2012
Withdrawn
March 2011

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.