πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Kent South

Kent South is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Sep 2010 (completed)
  2. ConsentedAug 2013 (completed)
  3. Construction (completed)
  4. OperatingDec 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
650AB
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Henrietta-Tulare Lake 70kV
Location
Kings County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
8 September 2010
Agreement signed
2 August 2013
Proposed online date
December 2012
Came online
December 2014

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem