Solar project 298, Gallatin County

Solar project 298, Gallatin County is a 0.3 MW solar request built and operating in the West interconnection queue, in Gallatin County, Montana, connecting to NorthWestern Energy.

Queue statusOperating
  1. PlanningQueued Jul 2016 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
298
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Bozeman Westside Substation
Location
Gallatin County, Montana
Technology
Solar: 0.3 MW
Total requested
0.3 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
8 July 2016
Proposed online date
June 2016
Came online
June 2016

Location

Marker shows the centre of Gallatin County; the queue data does not give exact sites.