United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· MISO

Onshore wind project J719, Codington County

Onshore wind project J719, Codington County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Codington County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2016 (completed)
  2. Withdrawn / abandonedMay 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J719
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Codington County, South Dakota
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
12 October 2016
Proposed online date
September 2018
Withdrawn
May 2017

Location

Marker shows the centre of Codington County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Codington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem