BATTERY STORAGE · ERCOT

Prairie Creek BESS

Prairie Creek BESS is a 10.0 MW battery storage request built and operating in the ERCOT interconnection queue, in Dallas County, Texas.

Queue statusOperating
  1. PlanningQueued Jan 2024 (completed)
  2. ConsentedMay 2024 (completed)
  3. Construction (completed)
  4. OperatingJul 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0662
Grid region
ERCOT (Texas)
Developer
SMT Dallas LLC
Connection point (POI)
Station Name: PRCK_x000D_ Load Name: LDLXFMR4_x000D_ XFMR Number: 4_x000D_ Bus number: 2762_x000D_ Voltage: 138 kV
Location
Dallas County, Texas
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
MRD Approved
Queue status
Operational
Entered queue
25 January 2024
Agreement signed
20 May 2024
Proposed online date
September 2025
Came online
July 2025

Location

Marker shows the centre of Dallas County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Dallas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem