ONSHORE WIND · CAISO

Wind Wall Monolith 2

Wind Wall Monolith 2 is a 3.7 MW onshore wind request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Apr 2018 (completed)
  2. ConsentedApr 2020 (completed)
  3. Construction (completed)
  4. OperatingMar 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1440
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Vincent Substation 220kV
Location
Kern County, California
Technology
Wind: 3.7 MW
Total requested
3.7 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
17 April 2018
Agreement signed
1 April 2020
Proposed online date
December 2019
Came online
March 2021

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem