United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Rio Bravo Solar I

Rio Bravo Solar I is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2010 (completed)
  2. Withdrawn / abandonedMar 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
655
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Westpark-Magunden 115 kV
Location
Kern County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
11 November 2010
Proposed online date
May 2013
Withdrawn
March 2011

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem