πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

SOLAR Β· NYISO

Lacona Solar

Lacona Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Oswego County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedDec 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
901
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
TJA Clean Energy, LLC
Connection point (POI)
Lighthouse Hill - Black River 115kV
Location
Oswego County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
16 August 2019
Withdrawn
December 2021

Location

Marker shows the centre of Oswego County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Oswego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem